Farrans is at present engaged on the Section 1 terminal extension, which is scheduled for completion in the summertime of 2025.
Below the brand new Section 2 contract, Farrans will concentrate on refurbishing the present terminal, with an anticipated completion date in winter 2026.
The renovation can be carried out in a number of sub-phases to minimise disruption for patrons and make sure that the airport can function as usually as doable.
Deliberate enhancements embrace the addition of recent staircases, lifts, and escalators to create a extra open and welcoming surroundings that enhances the brand new, brighter terminal extension.
The redesigned inner areas will improve passenger move, and new safety and arrivals amenities can be launched, together with World Responsibility Free outlets and varied bars and eating places.